The bill of materials, or BOM, is the complete list of components, materials and quantities needed to make an item. It is one of the most important documents in a manufacturing company: purchasing, cost calculation and production planning all start from it.
If the BOM is wrong, everything that follows is wrong: you buy the wrong material, get the quote wrong, stop production for a missing component.
This is the core guide: what a BOM is and which types of bill of materials exist. For the deep dives:
- Bill of materials example: three complete BOMs with tables, for machinery, footwear and food;
- Manufacturing BOM: how the engineering BOM (EBOM) becomes the BOM purchasing and production use (MBOM), and how to keep revisions aligned;
- Job order management: where the BOM drives the cost and lead time of a job.
What a bill of materials is
The bill of materials describes how a product is made: which parts it consists of, in what quantities and in what order they are assembled. For each component it records at least:
- item code;
- description;
- quantity per unit of finished product;
- unit of measure (pieces, metres, kg);
- level: whether it is a direct component or part of a sub-assembly.
In more structured companies the BOM also includes the preferred supplier, standard cost, expected scrap and the linked routing.
Bill of materials structure: levels
A simple product is enough to show the levels: a welded frame with mounting plates.
| Level | Code | Description | Qty | UoM |
|---|---|---|---|---|
| 0 | TL-100 | Complete welded frame | 1 | pc |
| 1 | TB-40 | 40x40 steel tube | 6 | m |
| 1 | PS-12 | Mounting plate | 2 | pc |
| 2 | LM-03 | S235 sheet, 3 mm | 0.4 | kg |
| 1 | VT-M6 | M6x20 screw | 12 | pc |
Level 0 is the finished product. Level 1 items are direct components. The plate (PS-12) is itself made in-house from sheet metal, so it has a level 2 beneath it. This tree structure is called a multi-level BOM.
In fashion and footwear the logic is the same, but the components change: upper, lining, sole, insole, trims. On top of that, every item has colour and size variants, and one model's BOM can become dozens of different BOMs. We cover this on the page for agents for footwear and contract fashion manufacturing.
This table only shows the structure. Three complete, sector-specific BOMs with every column filled in are in our bill of materials example guide.
Types of bill of materials
There are two ways to classify BOMs: by who uses them (engineering, production, sales, service) and by how they are structured (single-level, multi-level, configurable). A manufacturer usually has several of them for the same product.
By purpose
| Type | Who owns it | What it describes | Used for |
|---|---|---|---|
| Engineering BOM (EBOM) | Engineering | The product as designed, from the CAD drawing | Design, documentation, change control |
| Manufacturing BOM (MBOM) | Production engineering | The product as it is built: sub-assemblies, semi-finished parts, consumables, scrap | Purchasing, MRP, costing, shop floor |
| Sales BOM | Sales | The product as it is sold: a kit or bundle shown as one item | Quotes, orders, invoicing |
| Service BOM | After-sales | The spare parts and replaceable modules | Spare parts catalogue, repairs |
By structure
- Single-level BOM: direct components only, without a tree structure. Useful for simple products or for purchased kits.
- Multi-level BOM: the full tree, with sub-assemblies that have their own BOMs. Essential when semi-finished parts are made in-house.
- Configurable (variant) BOM: one "master" BOM with rules that generate the right version for each size, colour or option. Common in footwear, furniture and machinery with options.
- Job order BOM: a copy of the standard BOM adapted to one customer order, typical of make-to-order and engineer-to-order work.
- Phantom BOM: a sub-assembly that is never stocked: it exists in the structure to group components, and production builds it straight into the parent.
Which type of BOM you actually need
| How you manufacture | The BOM type you need |
|---|---|
| Make-to-stock, few simple items | Single-level, even in Excel |
| Semi-finished parts made in-house | Multi-level, in the ERP |
| Make-to-order or to customer drawings | Job order BOM, derived from a standard one |
| Sizes, colours or options (footwear, fashion, furniture) | Configurable (variant) BOM |
| Engineering changes drawings often | Separate EBOM and MBOM, with revision control |
One of the most frequent mistakes is the step from engineering BOM to manufacturing BOM: the drawing changes, the revision in the ERP does not. The same frame shown line by line in both versions, and the rules for keeping them aligned, are in our guide to the manufacturing BOM.
How to build a bill of materials
In Excel
For simple products and few items, an Excel sheet works. A template that holds up has these columns: level, parent code, component code, description, quantity per parent, unit of measure, scrap %, total quantity (calculated with a formula: quantity per parent × parent quantity × (1 + scrap)), make or buy, and revision. Keep a single item list on a separate sheet with data validation on the code column, so nobody invents a second code for the same part.
The limit comes quickly: no link to stock, no warning when a component is used in ten other BOMs, and revisions handled by hand with file names like "bom_v3_final".
In the ERP
Almost every ERP has a BOM module linked to inventory, purchasing and MRP. It is the right solution, but it has a hidden cost: someone has to enter the BOM, line by line, starting from the technical drawing. For a product with fifty components that means hours of work and dozens of chances to get a code or quantity wrong.
The most common bill of materials mistakes
- Wrong or duplicate codes: the same component under two different codes, and the stock no longer adds up.
- Wrong quantities per unit: for example the quantity per batch entered as quantity per piece.
- Inconsistent units of measure: metres in the BOM, 6-metre bars in the orders.
- Misaligned revisions: the drawing is at revision C, the BOM in the ERP at B.
- Scrap not accounted for: the sheet metal you need is always more than the theoretical amount.
Each of these mistakes is discovered late: when a part is missing on the shop floor or when the final costing of the job order does not add up.
How an AI agent builds the BOM from the drawing
Entering the BOM is a perfect job for an AI agent: repetitive, document-based, with clear rules. The AI agent that builds the bill of materials from drawings, one of our agents:
- reads the technical drawing (including CAD files) and extracts components and quantities;
- matches every component to the item codes already in the ERP;
- prepares the bill of materials in the ERP, flagging new or doubtful components;
- checks revisions and gives warning when drawing and BOM are out of step.
Engineering checks the exceptions instead of copying lines. From there the BOM passes to the Purchasing Agent, which calculates requirements and prepares supplier orders.
Frequently asked questions
What is a bill of materials in simple terms?
It is the "recipe" of a product: the list of all the components and materials needed to make it, with quantities and the structure in which they are assembled.
What do EBOM and MBOM mean?
EBOM is the engineering bill of materials, the BOM as designed. MBOM is the manufacturing bill of materials, the BOM as built.
What are the main types of bill of materials?
By purpose: engineering BOM, manufacturing BOM, sales BOM and service BOM. By structure: single-level, multi-level, configurable (variant), job order and phantom BOMs. Most manufacturers use at least an EBOM and an MBOM for the same product.
Can you make a bill of materials in Excel?
Yes, for simple products. With many items, variants and revisions it is better to manage it in the ERP, linked to inventory and purchasing.
Want to see how the BOM Agent reads your drawings? Book a demo with one of your real drawings.