Excess and obsolete inventory: causes and how to clear it

Excess and obsolete inventory in a manufacturing SME: where it comes from, what it costs, how to find it with turnover and last movement, what to do.

Excess and obsolete inventory is the material that sits in the warehouse beyond what production will need in the coming months: components bought in extra because of a minimum order quantity, material from a superseded revision, semi-finished parts from a cancelled job order. In a small or mid-sized manufacturer it almost always comes from four causes (minimum lot sizes, bill of materials changes, cancelled orders, inflated forecasts). You find it by cross-checking stock, consumption and date of last movement, and you clear it in three ways: reuse on other job orders, return or swap with the supplier, write-down and sale. The cheapest option, though, is still not creating it in the first place.

This guide doesn't go back over minimum stock and reorder points: if you need those, they're in our guide to inventory management. Here we deal with what happens afterwards, when the shelves are full of codes nobody picks any more.

Excess, slow-moving and obsolete stock: the differences

The three terms are often used interchangeably, but they describe different situations, and they change what you should do.

Term What it means Shop-floor example What you usually do
Excess stock Quantity above expected requirements, on a code that's still in use 5,000 screws bought for a minimum lot, 400 used per month Stop reordering, consume it over time
Slow-moving stock A code that moves little compared with what's on hand A gasket used on a single product sold twice a year Cut stock, consider buying to order
Obsolete stock A code with no planned use left The 8 mm side panel after the BOM moved to 10 mm Reuse, return, write down, scrap

The distinction matters: excess stock on a live code clears itself if you stop reordering. An obsolete code doesn't: it stays there until someone makes a decision.

Where excess inventory comes from

Anyone who has spent a few years between the purchasing office and the shop floor knows excess stock doesn't appear by accident. It almost always has one of these origins.

Minimum order quantities and lot sizes

The supplier sells sheet metal in 2-tonne bundles, cardboard by the pallet, fabric by the roll. You need 300 metres, you buy 1,000 because the unit price is lower. On paper it's a saving. But if that material is used on just one item, the extra 700 metres sit on the shelf for a year or more. The price saving should be compared with the cost of holding the stock, which almost nobody does at the moment of ordering.

Bill of materials revisions

Engineering changes a component, the bill of materials moves to the next revision, but nobody checks what's still in stock of the old code, or which orders are still open. It's the sneakiest source of obsolete stock, because the decision is right from a technical point of view and nobody sees the cost it leaves downstream. We cover this in the post on the manufacturing BOM too: a revision that doesn't reach purchasing in time generates orders for material that will never be used.

Cancelled or reduced job orders

The customer cuts the order from 2,000 to 800 pieces, or cancels it. The specific material has already arrived, some semi-finished parts are already made. In contract manufacturing (footwear, fashion, build-to-print engineering) it happens often: the material is customised and has no second use.

Inflated forecasts and "peace-of-mind stock"

Sales forecasts a peak that never comes, or the department head orders double "because last time we ran out". It's understandable: anyone who has stopped a line for a component worth a few euros doesn't want it to happen again. But a safety stock set by gut feeling, across a hundred codes, becomes a full warehouse.

What excess inventory really costs

The cost of excess stock isn't just what you paid the supplier. There are at least five items:

  • tied-up capital: money already spent that doesn't come back until the material becomes a product that's been sold;
  • space: racking, square metres, sometimes an external rented warehouse;
  • handling and stocktaking: every code has to be counted, moved, searched for;
  • deterioration and obsolescence: materials that age (adhesives, paints, food, leather), models that go out of fashion;
  • opportunity cost: the space and cash you don't have for the materials you actually need.

A worked example (hypothetical figures, just to give an order of magnitude). A company has raw material stock valued at €1,200,000. Looking at movements, it finds that 18% of that value, €216,000, sits on codes with no issues in the last 12 months. If we assume that holding material costs 20% of its value each year in capital, space and handling, that €216,000 costs around €43,000 a year, for material nobody uses. The real percentage varies a lot between companies: it's worth working it out with your own controlling team.

How to identify excess and obsolete stock

You don't need new software for a first analysis: three exports from the ERP (stock by code, consumption over the last 12 months, date of last movement) and a spreadsheet are enough.

1. Turnover and days of cover

  • Inventory turnover = annual consumption / average stock. A code with a turnover of 0.5 stays in the warehouse for two years on average.
  • Days of cover = current stock / average daily consumption. If a code covers 600 days of production and the supplier delivers in 30, you have excess stock.

2. Date of last movement

It's the simplest filter and the one that turns up most results: every code with no issues for 6, 12 or 24 months. Watch out for false positives: spare parts for after-sales and materials for long-cycle job orders move slowly but are still needed.

3. Cross-check against BOMs and open orders

A code with no movement is suspicious, but it becomes a certainty when it appears in no active BOM and no open customer order. This is the check that takes longest by hand, because you have to cross three different sources code by code. It's also the most useful.

The result is a list in three bands: live codes with too much stock, slow codes to keep an eye on, codes with no use that need a decision.

What to do with excess inventory

For each code on the list, assess the options in this order, from cheapest to most expensive.

  1. Stop reordering. It sounds obvious, but you do find open orders on codes already in excess, generated by a reorder point nobody updated.
  2. Reuse on other job orders. Engineering checks whether the material can replace an equivalent code in another BOM (same sheet metal, same fabric for a different lining, same screw in another acceptable size). It's often the route that recovers most value.
  3. Offer it to the customer. In contract manufacturing, material specific to a cancelled order can be charged to or returned to the customer, if the contract allows it. It's worth putting this in your order terms beforehand, not afterwards.
  4. Return or swap with the supplier. Some suppliers take back standard, undamaged material, perhaps with a deduction or in exchange for an order on another code. It's easier to negotiate when the relationship is good and the material is still in their catalogue.
  5. Sell to third parties or stock buyers. For commercial materials there are stock buyers and resale platforms. You recover little, but you free up space.
  6. Write-down and scrapping. Accounting rules generally require stock to be valued at the lower of cost and net realisable value (IAS 2 under IFRS; in Italy, article 2426 of the Civil Code), so material with no use is usually written down. Decide timing and amounts with your accountant, who also knows the tax side. Scrapping costs money, but holding material for years that will never be used costs more.

How to prevent excess inventory upstream

Clearing stock always means a partial loss. The real work is upstream, at the points where excess stock is created:

  • when a BOM revision changes: before releasing the new revision, check stock and open orders of the outgoing code, and decide whether to use it up or block it;
  • when ordering with a minimum lot: show the buyer how many months of consumption the extra quantity covers, not just the discount;
  • when a job order is reduced or cancelled: check straight away which supplier orders can still be reduced or cancelled, rather than finding out when the goods arrive (see also our guide to supplier order confirmations);
  • every month: a short but regular review of codes with no movement, instead of a one-off analysis once a year at stocktake.

These are simple checks. The problem is that they involve three different departments (engineering, purchasing, production) and none of the three sees all of them.

Where AI agents help

This is where our agents work, inside the ERP the company already uses and without changing how people work:

  • the BOM Agent, when a revision changes a component, flags stock and open orders of the outgoing code;
  • the Purchasing Agent records goods receipts from the supplier's delivery note, so stock is up to date, and warns when an order would push a code beyond its planned cover;
  • the Production Agent compares open job order requirements with stock and surfaces the codes no job order will use;
  • Octopus, the coordinator that makes them work together, connects the events: if a job order is reduced, it immediately alerts purchasing to supplier orders that can still be changed.

The decision on what to reuse, return or write down stays with people. The agents do the cross-checking that takes days by hand, and they do it every day rather than once a year.

Frequently asked questions

What is excess and obsolete inventory?

It's material in stock beyond the requirements of the coming months: material bought in excess, leftovers from cancelled job orders, or components superseded by a bill of materials revision.

How do you calculate inventory turnover?

Divide a code's annual consumption by its average stock over the same period. A low figure (below 1) means the material sits in the warehouse for more than a year.

When does stock become obsolete?

There's no single threshold: many companies use 12 or 24 months with no movement, but the deciding test is that the code appears in no active BOM and no open order.

Does obsolete stock have to be written down?

Stock is valued at the lower of cost and net realisable value, so material with no use is usually written down. Timing and amounts are decided with your accountant.